Livingston 2018 CIP – Meeting #4

TDH project update Work on water in Callender & Lewis Streets progressing COP construction update: Next week crews will be working storm drain in Callender and Lewis Two weeks out is sewer in Main Street and start of street reconstruction in Callender Street COP will provide updated construction schedule next week and will distribute to…

Read More

Livingston 2018 CIP – Meeting #3

TDH project update: Work on water in Callender Street progressing Couple issues we are working through with COP and CoL Private gas service last week Unknown sewer line Monday 2nd water crew to start in Lewis Street today COP construction update: Friday the water crew in Callender Street anticipates crossing Main Street COP anticipated removing…

Read More

Livingston 2018 CIP – Meeting #2

TDH project update: Change in conditions on the project – concrete under asphalt throughout project limits. COP will saw cut asphalt and concrete and remove material in trucks. Weather last week and forecasted for end of this week may slow progress. COP construction update: This week is water in Callender. Completing the connection to existing…

Read More

Livingston 2018 CIP – Meeting #1

Introductions: Keith Waring – TD&H Engineering Matt McGee – TD&H Engineering Matt Whitman – City of Livingston Eric Smith – COP Construction Steve Raudenbush – COP Construction Reedie Spencer – COP Construction TD&H project update: Snow has slowed the start of the project but asphalt pulverizing expected to start today. TD&H has completed a project…