TDH project update:

Change in conditions on the project – concrete under asphalt throughout project limits.

COP will saw cut asphalt and concrete and remove material in trucks.

Weather last week and forecasted for end of this week may slow progress.

COP construction update:

This week is water in Callender. Completing the connection to existing main in 2nd and Callender today.

A second crew is likely mobilizing to the site next week to start on water in Lewis.

After water improvements, COP will focus on street and sidewalk demolition, storm drain improvements and then rebuilding the road and sidewalk in Lewis and Callender before moving over to Main Street.

If businesses can communicate deliveries ahead of time with City and Contractor, that would be appreciated.

Traffic control concerns/comments:

Signage off Park Street is confusing and deterring business. COP will move signage back off Park Street to encourage traffic to turn in and will hang banners to communicate businesses are open.

Other items:

Horse ring has been donated to the project to replace the stolen item in front of the Mint. Other historical items have been painted to alert public of items for salvage and reinstallation on the project.

Next public meeting is Wednesday April 18, 2018.  8:30 am at the Livingston Center for Art & Culture, 119 S. Main Street