TDH project update

Work on water in Callender & Lewis Streets progressing

COP construction update:

Next week crews will be working storm drain in Callender and Lewis

Two weeks out is sewer in Main Street and start of street reconstruction in Callender Street

COP will provide updated construction schedule next week and will distribute to downtown and have on project website

We do have money to create additional project signs to advertise that downtown is open and accessible

Public comment

Critical to downtown businesses for traffic control to maintain access on one end of Main Street at all time

Downtown would like to see website advertised on weekly briefs

Next public meeting is Wednesday May 2, 2018. 8:30 am at the Livingston Center for Art & Culture, 119 S. Main Street