TDH project update:

Done with pipe this week, start demo in Callender next week. COP and TD&H will be working closely with each business to coordinate work. Project is on schedule.

COP construction update:

Anticipated schedule

COP will finish pipe this week and open Main Street and Lewis Street over the weekend. Callender between 2nd and B Streets will be closed during demo work, approximately 2 weeks. The curb and paving crews will come in behind street demolition. COP will maintain trench gravel on Main Street and Lewis Street during demo work on Callender. COP will introduce a new project superintendent next week for the street work.

Public Comment:

Several of the businesses expressed that they would like to be contacted ahead of work in front of their location. They are encouraged to get phone numbers of the City, TD&H or COP personnel and the team will work together to provide all the information possible.

Next public meeting is Wednesday May 23, 2018. 8:30 am at the Livingston Center for Art & Culture, 119 S. Main Street