Livingston 2018 CIP – Meeting # 16

TDH project update Paving underway, should be complete by Thursday morning.  Streets will be open for the weekend starting on Friday. COP construction update Anticipated schedule: Pavement and curb painting is scheduled for August 6th & 7th.  Streets will be closed during striping for these two days. Public Comment City will be out to place…

Read More

Livingston 2018 CIP – Meeting # 15

TDH project update Curb completed Working on sidewalk Paving next week COP construction update Anticipated schedule: Pave next Tuesday, 7/24 entire job will take 3 days likely.  Paver will start on west Callender and work down the street, south on the alley between Main and B, then on to Lewis Street and finish paving on…

Read More

Livingston 2018 CIP – Meeting #14

TDH project update High Country is finishing sidewalk in Callender Curb in Lewis and Main Street early next week COP construction update Anticipated schedule: Still planning to pave the entire project the week of July 23 Sidewalk work will continue after paving for likely 2 weeks Traffic control will expand during curb on Main and…

Read More