Livingston 2018 CIP – Meeting #14

TDH project update

  1. High Country is finishing sidewalk in Callender
  2. Curb in Lewis and Main Street early next week

COP construction update

Anticipated schedule:

  1. Still planning to pave the entire project the week of July 23
  2. Sidewalk work will continue after paving for likely 2 weeks
  3. Traffic control will expand during curb on Main and Lewis and will remain closed for final road gravel preparation and paving

Next public meeting is Wednesday July 18, 2018.  8:30 am at the Pickle Barrel on Main Street