City of Livingston

Livingston 2018 CIP – Meeting # 15

TDH project update

  1. Curb completed
  2. Working on sidewalk
  3. Paving next week

COP construction update

Anticipated schedule:

  1. Pave next Tuesday, 7/24 entire job will take 3 days likely.  Paver will start on west Callender and work down the street, south on the alley between Main and B, then on to Lewis Street and finish paving on Main Street
  2.  Streets will be open to traffic for a week or so before being closed again for striping which will likely take 2 days
  3.  Sidewalk pouring will continue this Friday and for the following 2 weeks

Public Comment

Contractor continues to coordinate and communicate with businesses and public and work hard to complete project ahead of schedule

Next public meeting is Wednesday July 25, 2018,  8:30 am at the Pickle Barrel on Main Street and Lewis Street