City of Livingston

Livingston 2018 CIP – Meeting # 16

TDH project update

  1. Paving underway, should be complete by Thursday morning.  Streets will be open for the weekend starting on Friday.

COP construction update

Anticipated schedule:

  1. Pavement and curb painting is scheduled for August 6th & 7th.  Streets will be closed during striping for these two days.

Public Comment

City will be out to place benches, bike racks and trash receptacles in a couple weeks once contractor is finished and final walk through is complete.

Final weekly public meeting is Wednesday August 1, 2018.  8:30 am at the Pickle Barrel on Main Street and Lewis Street