Livingston 2019 CIP – Meeting #5

TD&H project update: Shifted bypass pumping up to shadow progress of new sewer.  Main Street intersection closed for the next several weeks. WMC project update: Plan to be working on sewer in Clark next week and will move to sewer in Main Street headed from Clark to Geyser next. Public Comment: Matt Whitman will get…

Read More

Livingston 2019 CIP – Meeting #3

TD&H project update: NWE moving gas in Clark today and tomorrow, Contractor working on water rehab in Clark Street, should finish today. WMC project update: Plan to be working on sewer in Clark next week. Next public meeting is Thursday April 18, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street

Read More

Livingston 2019 CIP – Meeting #2

TD&H project update: Contractor is mobilizing and starting work. WMC project update: Contractor is working with NorthWestern Energy to move a gas main that is obstructing rehabilitation work and wastewater bypass pumping.  Hoping to still start on removing sewer early next week.  Need to work with City to get vehicles in the work zone moved…

Read More

Livingston 2019 CIP – Meeting #1

TD&H project update: Cold weather has slowed the start of the project but mobilization and traffic control/bypass pumping expected to start today.  Same timing on the start as last year = approximately same initial schedule, weather dependent WMC project update: Mob and set up systems, start saw cutting.  Then move to utility improvements in Clark…

Read More