City of Livingston

Livingston 2019 CIP – Meeting #1

TD&H project update:

Cold weather has slowed the start of the project but mobilization and traffic control/bypass pumping expected to start today.  Same timing on the start as last year = approximately same initial schedule, weather dependent

WMC project update:

Mob and set up systems, start saw cutting.  Then move to utility improvements in Clark Street, 3-4 weeks.  Sidewalk removal later.  WMC will install gravel and maintain business access during construction.

Contractor preliminary schedule:

Week of 4/1/2019: Contractor to mobilize and set up traffic control.  First thing the contractor will saw cut sewer trench in Clark from alley to B Street.

Contractor plans to start replacing utilities in Clark Street starting on the east side and working west.  There will be a link to construction schedule and traffic control plan on the project website.  TD&H has completed a project website: improvelivingston.com

Delivery coordination through Steve R. (WMC).  Clarification that alleys are open for deliveries and parking.  WMC will maintain access to alley traffic when the streets are closed and will work with businesses on deliveries etc.

Project signage – business input for signs – content and location

Contractor will maintain pedestrian access to downtown at all times.

Upcoming events downtown:

Art Walks – 4th Friday of the month

Next public meeting is Thursday April 4, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street