Livingston 2019 CIP – Meeting #10

TD&H project update: Storm drain installation is progressing up Main Street from the creek.  Crew will drop back and install inlets.  Hope is to have SD complete by end of next week. WMC project update: Traffic control will remain the same now through the demolition phase of the project.  Contractor is planning to start demolition…

Read More

Livingston 2019 CIP – Meeting #8

TD&H project update: Contractor is working on sewer in Main Street heading north from Clark Street towards Lewis Street.  All main line is installed, contractor working on services.  Geyser intersection will be closed and rerouted from Friday 5/17 through Wednesday 5/22, approximately. WMC project update: Western will start on storm drain at Fleshman Creek next…

Read More

Livingston 2019 CIP – Meeting #7

TD&H project update: Sewer in Clark Street has been installed and tested.  Contractor is working on sewer in Main street heading south from Clark Street towards Geyser Street WMC project update: Geyser and Main intersection will be closed Friday 5/10 to tie in new sewer manhole. The City and Contractor will notify the school to…

Read More

Livingston 2019 CIP – Meeting #6

TD&H project update: Set mh #5 in Main Street & Clark Street intersection.  Working on sewer in Clark and then move to sewer in Main Street between Clark and Geyser WMC project update: Open B & Clark intersection next Monday Hope to complete Clark sewer next Tuesday Water shutdown for valve in alley behind Neptunes…

Read More