City of Livingston

Livingston 2019 CIP – Meeting #6

TD&H project update:

Set mh #5 in Main Street & Clark Street intersection.  Working on sewer in Clark and then move to sewer in Main Street between Clark and Geyser

WMC project update:

  • Open B & Clark intersection next Monday
  • Hope to complete Clark sewer next Tuesday
  • Water shutdown for valve in alley behind Neptunes scheduled for Friday, May 3 at 8 am

Public Comment:

Traffic control adjustments and signs.  Access for Nevin’s semi next Tuesday, 5/7.

Contractor will maintain pedestrian access to downtown at all times.  Safety reminder.

Next public meeting is Thursday May 9, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street