TD&H project update:

Contractor is working on sewer in Main Street heading north from Clark Street towards Lewis Street.  All main line is installed, contractor working on services.  Geyser intersection will be closed and rerouted from Friday 5/17 through Wednesday 5/22, approximately.

WMC project update:

Western will start on storm drain at Fleshman Creek next week and work north in Main Street.

Public Comment:

Access to Main Street north of Geyser will be available while contractor works on storm drain main.

Contractor will maintain pedestrian access to downtown at all times.  Safety reminder.