Livingston 2019 CIP – Meeting #13

TD&H project update: Demo in Main Street nearly complete.  Contractor will demo Clark Street between now and end of next week.  Paving contractor is scheduled to be on site the second week of July to start working on curb. WMC project update: Traffic control will remain the same now through the demolition phase of the…

Read More

Livingston 2019 CIP – Meeting #12

TD&H project update: Demo has in Main Street.  Contractor will demo the west half of Main Street from Lewis down to Geyser and then switch to the east side of the street and demo back up to Lewis.  Paving contractor is scheduled to be on site the second week of July to start working on…

Read More

Livingston 2019 CIP – Meeting #9

TD&H project update: Contractor is working on sewer in Main Street heading north from Clark Street towards Lewis Street.  All main line is installed, contractor working on services.  Geyser intersection will be closed and rerouted from Friday 5/17 through Wednesday 5/22, approximately. WMC project update: Western will start on storm drain at Fleshman Creek next…

Read More

Livingston 2019 CIP – Meeting #11

TD&H project update: Storm drain installation is now in Clark Street and then will be completed.  Demo will start next week WMC project update: Traffic control will remain the same now through the demolition phase of the project.  Contractor is planning to start demolition the week of June 10 and will begin on Clark Street…

Read More

Livingston 2019 CIP – Meeting #11

TD&H project update: Storm drain installation is now in Clark Street and then will be completed.  Demo will start next week WMC project update: Traffic control will remain the same now through the demolition phase of the project.  Contractor is planning to start demolition the week of June 10 and will begin on Clark Street…

Read More