City of Livingston

Livingston 2019 CIP – Meeting #12

TD&H project update:

Demo has in Main Street.  Contractor will demo the west half of Main Street from Lewis down to Geyser and then switch to the east side of the street and demo back up to Lewis.  Paving contractor is scheduled to be on site the second week of July to start working on curb.

WMC project update:

Traffic control will remain the same now through the demolition phase of the project.

Paving the trench east of B Street on Clark and the Geyser intersection and south to Fleshman Creek in Main Street is delayed and may be completed as the rest of the job is paved at a later date.  Contractor anticipates all of Main Street will be graveled prior to July 4th week when they are not working.  City, Engineer and Contractor will walk the site prior to the July 4th week to make sure it is appropriate for parade activities.

Public comment:

First art walk is the fourth Friday of June.  Senior Center – flag pole, traffic signage and sidewalk demolition continued coordination.

Contractor will maintain pedestrian access to downtown at all times.  Safety reminder.

Next public meeting is Thursday June 20, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street