TD&H project update:

Demo complete.  Electrical contractor is installing light pole bases and conduit this week.  Paving contractor is scheduled to be on site the third week of July to start working on curb.

WMC project update:

Traffic control will be removed from the project on Friday, 6/28 in the afternoon prior to the art walk.  Project limits will be open to traffic over the week of July 4th.  Contractor will not be working next week.

Public comment:

First art walk is the fourth Friday of June (TMRW).

Contractor will maintain pedestrian access to downtown at all times.  Safety reminder.

Next public meeting is Thursday July 11, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street