City of Livingston

Livingston 2019 CIP – Meeting #15

TD&H project update:

Demo complete.  Electrical contractor finishing underground work this week.  Paving contractor will be installing curb next Tuesday and Wednesday (7/16-7/17).  The project limits will be closed to traffic.  The paving contractor will remain onsite installing sidewalk after curb in complete.

WMC project update:

Traffic control will be removed from the project on Friday, 6/28 in the afternoon prior to the art walk.  Project limits will be open to traffic over the week of July 4th.  Contractor will not be working next week.

Public comment:

Art walk is the fourth Friday of the month.

Contractor will maintain pedestrian access to downtown at all times.  Safety reminder.

Next public meeting is Thursday July 18, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street