Livingston Park Street Water | Weekly update #2

Progress update: Western Municipal set up traffic control and began staging equipment and material last week. Traffic control plan was approved on Monday 9/23 and work began to shut down the 10” water main in Park Street prior to installing a new 10” valve to isolate the bursting limits. Contractor is preparing the bursting pits…

Read More

Livingston Park Street Water | Weekly update #1

Project Description: Livingston Park Street Water Improvements. Work to be performed includes: The replacement of 10” diameter water mains using pipe bursting, fittings, valves, water service connections to the new water main, bedding material, backfill, compaction testing, concrete curb (straight) removal and replacement, asphalt removal and replacement, concrete removal and disposal and all other miscellaneous…