Livingston Park Street Water | Weekly update #1

Project Description: Livingston Park Street Water Improvements. Work to be performed includes: The replacement of 10” diameter water mains using pipe bursting, fittings, valves, water service connections to the new water main, bedding material, backfill, compaction testing, concrete curb (straight) removal and replacement, asphalt removal and replacement, concrete removal and disposal and all other miscellaneous work related to construction of a complete and operable water and street system on Park Street between 6th Street and 10th Street.

Progress update: Western Municipal Construction, Inc. has been awarded the project. Pre-construction conference held at public works with City, MDT, contractor and engineer on September 11, 2019. Contractor has submitted traffic control and MDT review comments have been received and incorporated into the plan.

Look ahead: Contractor plans to start setting up traffic control and staging equipment and material on Wednesday September 18 or Thursday September 19. Pipe bursting is expected to start early the week of September 23 on the 10th Street side of Park Street and working towards intersection of Park Street and 6th Street.

Click the links below to download construction and traffic control plans:

Final Construction Plans
Park St – Lane Push
Hwy 10 & Park St – Island