Progress update: Western has completed the water main connections and is completing the install of a new fire hydrant along Park Street. The tie-in at Hwy 10 is complete. The area is flow filled up to finish grade and Contractor will open the intersection completely for the weekend.

Look ahead: Contractor plans to test out water main early next week and then begin surface restoration (curb and asphalt).