Skip to content
Date:July 9, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #1TDH
Job No.:
B19-107

Introductions:
Matt McGee – TD&H Engineering
Shannon Holmes – City of Livingston Public Works
Ryan Drake – TD&H Engineering
Mike Kirkpatrick – TD&H Engineering
Byron Omdahl – Omdahl Excavation

TD&H project update: Demo has started in Callender.  Shannon gave a background of the project and summary of the public meeting.

Omdahl project update: Mob and set up systems, start saw cutting.  Domolition on the 2nd block of 2nd Street down to Lewis the rest of this week.

Then move to utility improvements in Callender Street. 

Contractor preliminary schedule:

Week of 7/13: Finish demolition of street and sidewalk in 2nd Street between Callender and Lewis.  Work on utilities in Callender.

Look ahead:  Probably 4-5 weeks before demolition will start on the block of 2nd Street between Park and Callender.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday July 16 4, 2020 @ 8:30 am 2nd Street Bistro.

Construction plans and project contact information will be posted in the windows of the 2nd Street Bistro.