Date:July 16, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #2TDH
Job No.:
B19-107

TD&H project update: Demo has completed in Callender and continues in 2nd Street.  Utilities in Callender are next and then SD in 2nd Street.

Omdahl project update:                               

Contractor preliminary schedule:

Week of 7/20: Water in Callender

Look ahead:  Looking to close the intersection of 2nd and Lewis starting the week of 7/27.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday July 23 4, 2020 @ 8:30 am 2nd Street Bistro.

Construction plans and project contact information will be posted in the windows of the 2nd Street Bistro.