Date:July 23, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #3TDH
Job No.:
B19-107

TD&H project update: Contractor finished water replacement in Callender Street.  Working on storm drain in 2nd Street from Callender down to Lewis. 

Omdahl project update: Planning to shut down the intersection at Lewis and 2nd Monday, 7/27.  This intersection will be closed until it is paved back, probably mid-August at the earliest.      

Contractor preliminary schedule:

Week of 7/27: Close intersection of 2nd and Lewis, work on storm drain in the intersection and lighting on 2nd Street.  Temporary water shutdown in the 2nd & 3rd Street alley behind First Interstate Bank on Monday, 7/27.  This will be a 4-hour shut down to tie onto the existing water main and the Contractor/City will give notice and coordinate with the impacted users.

Look ahead:  Omdahl is planning to start demo on the 100 block of 2nd Street the second week in August tentatively.  Traffic control will shift from current configuration to having the entire project limits closed until the 200 block of 2nd Street and the block of Callender can be paved back and opened up.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday July 30 4, 2020 @ 8:30 am 2nd Street Bistro.

Construction plans and project contact information will be posted in the windows of the 2nd Street Bistro.