Date:July 30, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #4TDH
Job No.:
B19-107

TD&H project update: Contractor working on intersection of 2nd and Lewis. 

Omdahl project update:  Completed water shut down in alley on Monday.

Contractor preliminary schedule:

Week of 8/3: Finish storm drain in intersection and work on lighting and prepare for curb.  Utility crew will shift up to alley behind First Interstate Bank to finish water and sewer replacement.

Look ahead:  Omdahl is planning to start demo on the 100 block of 2nd Street the second week in August tentatively.  Traffic control will shift from current configuration to having the entire project limits closed until the 200 block of 2nd Street and the block of Callender can be paved back and opened up.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday August 6, 2020 @ 8:30 am 2nd Street Bistro.

Construction plans and project contact information will be posted in the windows of the 2nd Street Bistro.