Date:August 6, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #5TDH
Job No.:
B19-107

TD&H project update: Contractor working on intersection of 2nd and Lewis. Will finish up in intersection this week and start preparing for curb next week

Omdahl project update: Plan is to have High Country Paving mobilize onto the job mid-to-late next week to install curb in intersection at 2nd and Lewis up to Callender Street.

Contractor preliminary schedule:

Week of 8/10: Finish utilities in alley and move to demo in north 2nd Street.

Look ahead:  Omdahl is planning to start demo on the 100 block of 2nd Street the second week in August tentatively.  Traffic control will shift from current configuration to a more comprehensive shutdown as shown on the attached exhibit.  There will be access to the post office and bank parking lot through the intersection of Callender and 2nd Street for a limited time.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday August 13, 2020 @ 8:30 am 2nd Street Bistro.

Construction plans and project contact information will be posted in the windows of the 2nd Street Bistro.