TD&H project update: Preparing for curb installation in 2nd Street. Started demo in 100 block of 2nd Street with new traffic control in place.

Omdahl project update: Vault is filled, will finish utilities in alley next week.

Contractor preliminary schedule:

Week of 8/17: Finish utilities in alley and move to demo in north 2nd Street.

Look ahead:  Finish demo in 2nd Street and start utilities.  Curb in 2nd Street from Lewis up to Callender early next week.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday August 20, 2020 @ 8:30 am 2nd Street Bistro.