Date:August 20, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #7TDH
Job No.:
B19-107

TD&H project update: Preparing for curb installation in 2nd Street. Started demo in 100 block of 2nd Street with new traffic control in place.

Omdahl project update: Pave Lewis & 2nd Intersection mid-next week hopefully. May also pave up 2nd Street to Callender. Will give businesses notice prior to installing sidewalk in front as they move up 2nd Street.

Contractor preliminary schedule:

Week of 8/17: Finish utilities in alley and move to demo in north 2nd Street.

Look ahead:  Finish demo in 2nd Street and start utilities.  Curb in 2nd Street from Lewis up to Callender early next week.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday August 27, 2020 @ 8:30 am 2nd Street Bistro.