Date:August 27, 2020Time:8:30 am
Subject:Livingston CIP |  Public Meeting #8TDH
Job No.:
B19-107

TD&H project update:

Omdahl project update: Will finish utilities in alley next week this week hopefully. Plan is to pave between Callender and Lewis on Friday, 8/28, weather permitting. The block will then be open to traffic starting next week.

Contractor preliminary schedule:

Week of 9/2: Finish utilities in alley and move to utilities in north 2nd Street.

Look ahead:  Finish utilities in 2nd Street and start sidewalk demo.  Curb in Callender Street in the next week or two.

Contractor will maintain pedestrian access to downtown at all times.

Next public meeting is Thursday September 3, 2020 @ 8:30 am 2nd Street Bistro.

Construction plans and project contact information will be posted in the windows of the 2nd Street Bistro.