Livingston 2020 CIP – Meeting #8

Date: August 27, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #8 TDHJob No.: B19-107 TD&H project update: Omdahl project update: Will finish utilities in alley next week this week hopefully. Plan is to pave between Callender and Lewis on Friday, 8/28, weather permitting. The block will then be open to traffic starting…

Read More

Livingston 2020 CIP – Meeting #7

Date: August 20, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #7 TDHJob No.: B19-107 TD&H project update: Preparing for curb installation in 2nd Street. Started demo in 100 block of 2nd Street with new traffic control in place. Omdahl project update: Pave Lewis & 2nd Intersection mid-next week hopefully. May also pave…

Read More

Livingston 2020 CIP – Meeting #6

Date: August 13, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #6 TDHJob No.: B19-107 TD&H project update: Preparing for curb installation in 2nd Street. Started demo in 100 block of 2nd Street with new traffic control in place. Omdahl project update: Vault is filled, will finish utilities in alley next week. Contractor…

Read More

Livingston 2020 CIP – Meeting #5

Date: August 6, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #5 TDHJob No.: B19-107 TD&H project update: Contractor working on intersection of 2nd and Lewis. Will finish up in intersection this week and start preparing for curb next week Omdahl project update: Plan is to have High Country Paving mobilize onto the…

Read More

Livingston 2020 CIP – Meeting #4

Date: July 30, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #4 TDHJob No.: B19-107 TD&H project update: Contractor working on intersection of 2nd and Lewis.  Omdahl project update:  Completed water shut down in alley on Monday. Contractor preliminary schedule: Week of 8/3: Finish storm drain in intersection and work on lighting and…

Read More

Livingston 2020 CIP – Meeting #3

Date: July 23, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #3 TDHJob No.: B19-107 TD&H project update: Contractor finished water replacement in Callender Street.  Working on storm drain in 2nd Street from Callender down to Lewis.  Omdahl project update: Planning to shut down the intersection at Lewis and 2nd Monday, 7/27.  This…

Read More

Livingston 2020 CIP – Meeting #2

Date: July 16, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #2 TDHJob No.: B19-107 TD&H project update: Demo has completed in Callender and continues in 2nd Street.  Utilities in Callender are next and then SD in 2nd Street. Omdahl project update:                                Contractor preliminary schedule: Week of 7/20: Water in Callender Look…

Read More

Livingston 2020 CIP – Meeting #1

Date: July 9, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #1 TDHJob No.: B19-107 Introductions:Matt McGee – TD&H EngineeringShannon Holmes – City of Livingston Public WorksRyan Drake – TD&H EngineeringMike Kirkpatrick – TD&H EngineeringByron Omdahl – Omdahl Excavation TD&H project update: Demo has started in Callender.  Shannon gave a background of the…

Read More

Livingston Park Street Water | Weekly update #4

Progress update: Western has completed the water main connections and is completing the install of a new fire hydrant along Park Street. The tie-in at Hwy 10 is complete. The area is flow filled up to finish grade and Contractor will open the intersection completely for the weekend. Look ahead: Contractor plans to test out water…

Read More