Skip to content

Livingston 2020 CIP – Meeting #4

Date: July 30, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #4 TDHJob No.: B19-107 TD&H project update: Contractor working on intersection of 2nd and Lewis.  Omdahl project update:  Completed water shut down in alley on Monday. Contractor preliminary schedule: Week of 8/3: Finish storm drain in intersection and work on lighting and…

Read More

Livingston 2020 CIP – Meeting #3

Date: July 23, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #3 TDHJob No.: B19-107 TD&H project update: Contractor finished water replacement in Callender Street.  Working on storm drain in 2nd Street from Callender down to Lewis.  Omdahl project update: Planning to shut down the intersection at Lewis and 2nd Monday, 7/27.  This…

Read More

Livingston 2020 CIP – Meeting #2

Date: July 16, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #2 TDHJob No.: B19-107 TD&H project update: Demo has completed in Callender and continues in 2nd Street.  Utilities in Callender are next and then SD in 2nd Street. Omdahl project update:                                Contractor preliminary schedule: Week of 7/20: Water in Callender Look…

Read More

Livingston 2020 CIP – Meeting #1

Date: July 9, 2020 Time: 8:30 am Subject: Livingston CIP |  Public Meeting #1 TDHJob No.: B19-107 Introductions:Matt McGee – TD&H EngineeringShannon Holmes – City of Livingston Public WorksRyan Drake – TD&H EngineeringMike Kirkpatrick – TD&H EngineeringByron Omdahl – Omdahl Excavation TD&H project update: Demo has started in Callender.  Shannon gave a background of the…

Read More

Livingston Park Street Water | Weekly update #4

Progress update: Western has completed the water main connections and is completing the install of a new fire hydrant along Park Street. The tie-in at Hwy 10 is complete. The area is flow filled up to finish grade and Contractor will open the intersection completely for the weekend. Look ahead: Contractor plans to test out water…

Read More

Livingston Park Street Water | Weekly update #3

Progress update: All of the new HDPE pipe has been installed to replace the old cast iron pipe in Park Street. The contractor finished installing new 10” water main in Park Street today. Look ahead: Contractor will work on installing the new fire hydrant and connecting the new water main to existing system next week.…

Read More

Livingston Park Street Water | Weekly update #2

Progress update: Western Municipal set up traffic control and began staging equipment and material last week. Traffic control plan was approved on Monday 9/23 and work began to shut down the 10” water main in Park Street prior to installing a new 10” valve to isolate the bursting limits. Contractor is preparing the bursting pits…

Read More

Livingston Park Street Water | Weekly update #1

Project Description: Livingston Park Street Water Improvements. Work to be performed includes: The replacement of 10” diameter water mains using pipe bursting, fittings, valves, water service connections to the new water main, bedding material, backfill, compaction testing, concrete curb (straight) removal and replacement, asphalt removal and replacement, concrete removal and disposal and all other miscellaneous…

Read More

Livingston 2019 CIP – Meeting #18

TD&H project update: Treasure State has finished pouring curb on the project.  They are now pouring sidewalks. Steve from Western will be stopping by before they pour sidewalks to discuss business access pouring sidewalk pouring.  When sidewalks have been newly poured please help us keep an eye out for anyone attempting to write in the…

Read More