Livingston 2018 CIP – Meeting #17

TDH project update Paving complete Sidewalks complete COP construction update Anticipated schedule: Striping August 7 Signage August 21 Closure at main and callender to fix ADA grade issue Hope to open Main by weekend Finish lighting this week No more public meeting scheduled for this project.  Please follow the website and City Facebook page for…

Read More

Livingston 2018 CIP – Meeting # 16

TDH project update Paving underway, should be complete by Thursday morning.  Streets will be open for the weekend starting on Friday. COP construction update Anticipated schedule: Pavement and curb painting is scheduled for August 6th & 7th.  Streets will be closed during striping for these two days. Public Comment City will be out to place…

Read More

Livingston 2018 CIP – Meeting # 15

TDH project update Curb completed Working on sidewalk Paving next week COP construction update Anticipated schedule: Pave next Tuesday, 7/24 entire job will take 3 days likely.  Paver will start on west Callender and work down the street, south on the alley between Main and B, then on to Lewis Street and finish paving on…

Read More

Livingston 2018 CIP – Meeting #14

TDH project update High Country is finishing sidewalk in Callender Curb in Lewis and Main Street early next week COP construction update Anticipated schedule: Still planning to pave the entire project the week of July 23 Sidewalk work will continue after paving for likely 2 weeks Traffic control will expand during curb on Main and…

Read More

Livingston 2018 CIP – Meeting #13

TDH project update: Sidewalks in Callender No meeting next week COP construction update: Anticipated schedule High Country crews will pour as much sidewalk as possible this week Contractor anticipating to pave entire project week of July 23 COP will be on site Mon, Tues, Thurs, Fri next week early morning to check streets and water…

Read More

Livingston 2018 CIP – Meeting #12

TDH project update Curb in Callender COP construction update Anticipated schedule: One block of curb in Callender today – weather dependent Sidewalk in Callender next week, starting at the Mint Public Comment: First Art Walk is this Friday at 5:30 Next public meeting is Wednesday June 27, 2018. 8:30 am at the Livingston Center for…

Read More

Livingston 2018 CIP – Meeting #11

TDH project update Demo on Lewis finished Start demo on Main Flat work – Curb starting Theft of curb stakes COP construction update Anticipated schedule: Finish demo on Main street this week High Country paving should be onsite Thursday 6/14 Ideally start pouring curb on Callender Friday 6/15 Next public meeting is Wednesday June 20,…

Read More

Livingston 2018 CIP – Meeting #10

TDH project update: Demo on callender finished Start demo on Lewis Flat work – Curb starting Theft of project bench COP construction update: Anticipated schedule High Country on-site for curb prep next week Electricians to finish Callender mid next week COP complete with demo on Lewis by Friday this week COP complete with demo in…

Read More

Livingston 2018 CIP – Meeting #9

TDH project update: Demo on Callender continued. COP Construction update: Anticipated schedule End of week or early next week finish demo work in Callender. Lewis is next for demo. Ideally, COP is finished with all demo by end of June, weather dependent. Electricians have started work in Callender behind demo. Traffic control concerns/comments: COP will…

Read More