Livingston Park Street Water | Weekly update #4

Progress update: Western has completed the water main connections and is completing the install of a new fire hydrant along Park Street. The tie-in at Hwy 10 is complete. The area is flow filled up to finish grade and Contractor will open the intersection completely for the weekend. Look ahead: Contractor plans to test out water…

Read More

Livingston Park Street Water | Weekly update #3

Progress update: All of the new HDPE pipe has been installed to replace the old cast iron pipe in Park Street. The contractor finished installing new 10” water main in Park Street today. Look ahead: Contractor will work on installing the new fire hydrant and connecting the new water main to existing system next week.…

Read More

Livingston Park Street Water | Weekly update #2

Progress update: Western Municipal set up traffic control and began staging equipment and material last week. Traffic control plan was approved on Monday 9/23 and work began to shut down the 10” water main in Park Street prior to installing a new 10” valve to isolate the bursting limits. Contractor is preparing the bursting pits…

Read More

Livingston Park Street Water | Weekly update #1

Project Description: Livingston Park Street Water Improvements. Work to be performed includes: The replacement of 10” diameter water mains using pipe bursting, fittings, valves, water service connections to the new water main, bedding material, backfill, compaction testing, concrete curb (straight) removal and replacement, asphalt removal and replacement, concrete removal and disposal and all other miscellaneous…

Read More

Livingston 2019 CIP – Meeting #18

TD&H project update: Treasure State has finished pouring curb on the project.  They are now pouring sidewalks. Steve from Western will be stopping by before they pour sidewalks to discuss business access pouring sidewalk pouring.  When sidewalks have been newly poured please help us keep an eye out for anyone attempting to write in the…

Read More

Livingston 2019 CIP – Meeting #17

TD&H project update: Treasure State has finished pouring curb on the project.  They are now pouring sidewalks. Steve from Western will be stopping by before they pour sidewalks to discuss business access pouring sidewalk pouring.  When sidewalks have been newly poured please help us keep an eye out for anyone attempting to write in the…

Read More

Livingston 2019 CIP – Meeting #16

TD&H project update: Treasure State has finished pouring curb on the project.  Monday they will begin pouring sidewalks on Clark Street by Neptune’s.  They will work in the direction they poured curb, up Main to Lewis, back down the east side to Geyser and finishing up beside Wilcoxson’s.  Steve from Western will be stopping by…

Read More

Livingston 2019 CIP – Meeting #15

TD&H project update: Demo complete.  Electrical contractor finishing underground work this week.  Paving contractor will be installing curb next Tuesday and Wednesday (7/16-7/17).  The project limits will be closed to traffic.  The paving contractor will remain onsite installing sidewalk after curb in complete. WMC project update: Traffic control will be removed from the project on…

Read More

Livingston 2019 CIP – Meeting #14

TD&H project update: Demo complete.  Electrical contractor is installing light pole bases and conduit this week.  Paving contractor is scheduled to be on site the third week of July to start working on curb. WMC project update: Traffic control will be removed from the project on Friday, 6/28 in the afternoon prior to the art…

Read More