Livingston 2019 CIP – Meeting #7

TD&H project update: Sewer in Clark Street has been installed and tested.  Contractor is working on sewer in Main street heading south from Clark Street towards Geyser Street WMC project update: Geyser and Main intersection will be closed Friday 5/10 to tie in new sewer manhole. The City and Contractor will notify the school to…

Read More

Livingston 2019 CIP – Meeting #6

TD&H project update: Set mh #5 in Main Street & Clark Street intersection.  Working on sewer in Clark and then move to sewer in Main Street between Clark and Geyser WMC project update: Open B & Clark intersection next Monday Hope to complete Clark sewer next Tuesday Water shutdown for valve in alley behind Neptunes…

Read More

Livingston 2019 CIP – Meeting #5

TD&H project update: Shifted bypass pumping up to shadow progress of new sewer.  Main Street intersection closed for the next several weeks. WMC project update: Plan to be working on sewer in Clark next week and will move to sewer in Main Street headed from Clark to Geyser next. Public Comment: Matt Whitman will get…

Read More

Livingston 2019 CIP – Meeting #3

TD&H project update: NWE moving gas in Clark today and tomorrow, Contractor working on water rehab in Clark Street, should finish today. WMC project update: Plan to be working on sewer in Clark next week. Next public meeting is Thursday April 18, 2019 @ 8:30 am at ERA Landmark, 215 S. Main Street

Read More

Livingston 2019 CIP – Meeting #2

TD&H project update: Contractor is mobilizing and starting work. WMC project update: Contractor is working with NorthWestern Energy to move a gas main that is obstructing rehabilitation work and wastewater bypass pumping.  Hoping to still start on removing sewer early next week.  Need to work with City to get vehicles in the work zone moved…

Read More

Livingston 2019 CIP – Meeting #1

TD&H project update: Cold weather has slowed the start of the project but mobilization and traffic control/bypass pumping expected to start today.  Same timing on the start as last year = approximately same initial schedule, weather dependent WMC project update: Mob and set up systems, start saw cutting.  Then move to utility improvements in Clark…

Read More

Livingston 2018 CIP – Meeting #17

TDH project update Paving complete Sidewalks complete COP construction update Anticipated schedule: Striping August 7 Signage August 21 Closure at main and callender to fix ADA grade issue Hope to open Main by weekend Finish lighting this week No more public meeting scheduled for this project.  Please follow the website and City Facebook page for…

Read More

Livingston 2018 CIP – Meeting # 16

TDH project update Paving underway, should be complete by Thursday morning.  Streets will be open for the weekend starting on Friday. COP construction update Anticipated schedule: Pavement and curb painting is scheduled for August 6th & 7th.  Streets will be closed during striping for these two days. Public Comment City will be out to place…

Read More

Livingston 2018 CIP – Meeting # 15

TDH project update Curb completed Working on sidewalk Paving next week COP construction update Anticipated schedule: Pave next Tuesday, 7/24 entire job will take 3 days likely.  Paver will start on west Callender and work down the street, south on the alley between Main and B, then on to Lewis Street and finish paving on…

Read More

Livingston 2018 CIP – Meeting #14

TDH project update High Country is finishing sidewalk in Callender Curb in Lewis and Main Street early next week COP construction update Anticipated schedule: Still planning to pave the entire project the week of July 23 Sidewalk work will continue after paving for likely 2 weeks Traffic control will expand during curb on Main and…

Read More